Despite its innocent appearance, Section 8(1) of the Building and Construction Industry Security of Payment Act 1999 (NSW) (Act) has proven a complex, opaque and over-analysed provision. Although practically repealed by the 2018 Amending Act its original form will continue haunt us, and the hallways and court rooms in Phillip St, to gradually fade away as the years pass.
Section 8 in its previous form, and many of the judgments that have considered it, have derailed many payment claims, adjudication applications, adjudication determinations summary judgment applications and other enforcement action. It has embarrassed and frustrated many adjudicators, lawyers and claims consultants. It is not difficult to put the case that it has not served the object of the Act[1] particularly well, indeed it has often been its Achilless heel.
Contorting legal analysis lead to evolving, contorted, convoluted and at times conflicting judicial guidance often making legal advice like a form-guide. Right up there with and sometimes closely related to, the dramas and conflicting judicial guidance around repetitious claims.
This was recognised by the New South Wales Government so, for contracts entered into after 20 October 2019, reference dates are abolished and a new regime introduced, entitling a claimant to make a claim under section 13 on and from the last day of the month in which construction work was first carried out and on and from the last day of each subsequent month, unless the contract made provision for an earlier date.
However, the reference date zombies will continue to haunt pre-21 October 2019 contracts perplexing, frustrating and perhaps terrifying claimants for years to come.
The purpose of this insight is to make stakeholders[2] aware or perhaps remind them of the problems and complexities associated with the zombie reference dates and to remind us of some of the common and at times embarrassing hidden traps, so as to identify them early before adjudicators fees are incurred unnecessarily and avoid spraying the legal costs of defending invalid determinations to the wind.
The form of section 8 that applies to construction contracts entered into before 21 October 2019 is:
(1) On and from each reference date under a construction contract, a person:
(a) who has undertaken to carry out construction work under the contract, or
(b) who has undertaken to supply related goods and services under the contract,
is entitled to a progress payment.
(2) In this section, reference date, in relation to a construction contract, means:
(a) a date determined by or in accordance with the terms of the contract as the date on which a claim for a progress payment may be made in relation to work carried out or undertaken to be carried out (or related goods and services supplied or undertaken to be supplied) under the contract, or
(b) if the contract makes no express provision with respect to the matterthe last day of the named month in which the construction work was first carried out (or the related goods and services were first supplied) under the contract and the last day of each subsequent named month.
The form of section 8 that applies to construction contracts entered into on and from 21 October 2019 is simply:
8 Right to progress payments
A person who, under a construction contract, has undertaken to carry out construction work or to supply related goods and services is entitled to receive a progress payment.
For the sake of completeness, section 13 was also amended on and from 21 October 2019 to include the new subsections 13 (1A) (1C):
13 Payment claims
(1A) A payment claim may be served on and from the last day of the named month in which the construction work was first carried out (or the related goods and services were first supplied) under the contract and on and from the last day of each subsequent named month.
(1B) However, if the construction contract concerned makes provision for an earlier date for the serving of a payment claim in any particular named month, the claim may be served on and from that date instead of on and from the last day of that month.
(1C) In the case of a construction contract that has been terminated, a payment claim may be served on and from the date of termination.
Claims made before the applicable reference date
Many contracts, particularly those bespoke in nature, include a term to the effect that payment claims may be made monthly, on say the 25th day of each month, but then continue to provide that payment claims made before that date shall be deemed to have been made on the date for making that claim, or words to that effect.
However reference dates arise on and from the date determined by or in accordance with the terms of the contract as the date on which a claim for a progress payment may be made. The Supreme Court has held and the Court of Appeal has upheld the view that the deeming provisions, such as the above do not convert the reference date in to some earlier date.[3] This would also seem to be the case for contracts from 21 October 2019 onwards, although there is as yet no specific authority on that point.
A person that serves a payment claim relying on a clause deeming claims served early to be claims served on the reference date will not be a person referred to in section 8(1) who is entitled to a progress payment. They will instead likely be mauled by the zombie.
Milestone or stages as reference dates (or not)
Setting out percentages (or other amounts) of the contract sum payable upon the achievement of milestones or stages is problematic as zombie reference dates, for a number of reasons. Firstly, there is often room for argument as to whether a stage of the work has been completed or a milestone achieved, making it a rather vague, perhaps unreliable mechanism for establishing reference dates. An oft-cited example is Completion of brick works. It might be the case that all of the brick work will be completed other than the window sills, as that bit needs to be postponed to enable the flashing to be installed correctly when the windows are put in place. Strictly speaking, not all the brick work has been complete despite only perhaps 1% being postponed for very practical reasons.
Care needs to be taken to ensure that the provision specifying the amount or percentage of the contract sum claimable upon achievement of a stage or milestone actually addresses the date upon which a payment claim may be made. The amount payable upon reaching a stage and the date for claims are not necessarily the same thing. It may be that, if not addressed clearly, there will be scope for section 8(2)(b) to apply, which may not be desirable, particularly for a principal.
In Greenwood Futures v DSD Builders[4], the contract required the contractor to give the developer a written claim for progress payment for the completion of each identified stage of the works. McDougall J said[5] :
The only specification of when a progress claim may be submitted is that contained in clause 17.3. That sub clause contemplates that the stage in respect of which the progress payment is claimed will be complete. It requires the claim to be made for the completion of [that] stage. It does not say that the claim must be made immediately upon completion of that stage, or indeed any other date that is defined by reference to completion of that stage (for example, on the 30th day of the month in which completion of that stage is achieved). It may be assumed that a builder seeking to maintain its cash flow, will submit the progress claim as quickly as it can following completion of the stage to which it relates. But that does not enable the date for submission of the progress claim to be determined.
It is also worth bearing in mind that a provision which goes beyond fixing a mechanism for determining the date on which the contractor is to be paid, and which:
will or maybe invalidated by section 34[6] and it is often not terribly difficult for a claimant to convince an adjudicator that is the case.
Termination and taking the work out of the contractors hands
It has been accepted for sometime that, unless the contract provides to the contrary, if the contract was entered into before 21 October 2019, that no further reference dates will arise after its termination.[7]
So, if the contract was entered into before 21 October 2019 and the contract is terminated there may be a lacunae, where the last reference date has already been spent, in respect of work performed between that reference date and the date the contract is terminated.
If however, a reference date has accrued prior to the termination and it has not been spent, it may well still be available to base a payment claim under the Act after termination. The prevailing authority, Parwood[8] is that termination and taking the work out of the contractors hands does not effect rights that had accrued under the Act before suspension (and logically before termination). Ball J observed that there was nothing in the judgment in Southern Han[9] to suggest that what the High Court said was intended to affect rights that had accrued under the Act before suspension. He noted that the High Court said that no reference date and no right to a progress payment could be pursued after suspension, but found that does not prevent a party from pursuing a claim in respect of a right to a progress payment (reference date) that arose/accrued before suspension [and presumably termination].
Taking work out of the contractors hands: even a little bit of work
The High Court has mused that the cessation of reference dates also applies where only part of the work is taken out of the contractors hands and the contractor is obliged to complete the balance:
True it is that clause 39.4 would have permitted Southern Han to take only some of the work out of Lewences hands, in which case to interpret that clause as suspending payment for the work other than that taken out of Lewences hands would mean that Lewence would have been obliged to continue with other work for which it would not be paid until completion of the section 39.6 process [10]
That seems rather harsh, and is obiter, but the High Court saw it as justified, given that work could only in that contract be taken out of the contractors hands as a consequence of a substantial breach, which is not unusual.
The relationship between the work claimed and the reference date
The question often arises whether a payment claim can include items of work or construction related goods and services that were performed or provided after the reference date. Until very recently, authority on this point was hard to come by. The judgment of the Court of Appeal in Brolton Group Pty Ltd v Hanson Construction Materials Pty Ltd[11] clearly indicates that work performed or construction related goods and services provided after the reference date should not be included in the payment claim. That cases main claim to fame is that the adjudicator determined a reference date different to the dates propounded by either party, without seeking their submissions in respect of his preference found to be a failure of natural justice. However the Court of Appeal also found that the reference date determined by the adjudicator could not have been correct in any event. This was because the contract had been terminated by the Principal and the entitlement to progress claims under the contract did not survive termination and that gave rise to a jurisdictional error by the adjudicator.
The natural justice issue was that the adjudicator had determined it on a basis for which neither party had contended (i.e. reference date of 28 October 2018). At first instance, Ball J stated:
The choice of reference dates had a substantial effect on the outcome of the determination. It provided an answer to Hansons submissions that Brolton had made progress claims for work done after 25 September 2018, which were not permitted by the contract. It also provided an answer to Hansons submission that any claim for extensions of time and delay costs were only submitted after the reference date (on 28 September 2018). It follows that [by finding a reference date of 23 October 2018] there was a substantial denial of natural justice.
An implication of that seems to be that work done after the reference date and claims for extension of time and delay costs after the reference date are not validly included in the payment claim. The Court of Appeal agreed in considering whether the denial of natural justice was material. In a unanimous judgment the courts stated [at 68]:
The adjudicators decision to proceed on the basis of 23 October 2018 reference date was plainly material insofar as it substantially affected the quantum of the determination which the adjudicator purported to make. As the primary judge observed at [43], the choice of the later reference date provided an answer to Hansons submission that Broltons payment claim included claims for work done after a 25 September 2018 reference date, as well as claims for delay costs due to extensions of time which had not been the subject of any Variation Application made before that earlier reference date.
So not only is a claimant not entitled to claim work performed or construction related goods and services provided after the reference date in the payment claim, it is also not entitled to rely upon claims for extension of time or delay costs only submitted after the reference date.
However including work undertaken or claims for EOTs made after the reference date does not necessarily invalidate the payment claim. In the court below where Ball J held:
there was nothing in Southern Hand that requires for a payment claim to be valid, it must only relate to work done before the reference date in respect of which the payment claim was served [29];
the validity of the payment claim does not depend upon when the work it covered was performed [31];
This however only goes to the validity of the payment claim, as opposed to whether works performed after the reference date or notices served after the reference date should be taken into account in determining the payment claim and arriving at the adjudicated amount.
The reference date relied upon by the adjudicator
It is not compulsory for an adjudicator to identify the reference date upon which a payment claim is based, unless the existence of an available reference date is an issue in the adjudication[12].
If it is a matter in issue then the adjudicator must determine it. The adjudicator must not determine a date for which neither party has contended, unless the parties have been given the opportunity to make submissions in respect of the adjudicators theory. Failure to commit the parties to have a say in this exposes the determination to being challenged on the basis of a jurisdictional error and being found a failure by the adjudicator to apply the appropriate measure of natural justice. There is ample on this in the section above.
When a reference date will not be implied by section 8(2)(b)
If the construction contract entered into before 21 October 2019 addresses reference dates in a competent manner, then your stuck with it. It matters not that you cannot identify a date that works for your claim. The implication of a date under section 8(2)(b) is academic if the issue is addressed by the contract.
The Contract having made express provision in cl 37.1 fixing the date for the claiming of progress payments under the Contract, s 8(2)(b) could have no application. The requisite reference date was potentially capable of having arisen only in the application of s8(2)(a).[13]
The Ongoing Work Myth
There was, for a while, good authority for the proposition that a reference date did not arise where no construction work was carried out or related goods and services provided since the previous claim (which presumably relied upon a valid reference date).[14] This acted to prevent many repetitious claims progressing to adjudication and provided an answer to many summary judgment applications.
However that approach was, for present purposes, terminated in 2015 when McDougall J changed his mind, finding that a reference date does not have to be supported in the manner suggested above and that the only temporal limitation on reference dates and is that set out in the section 13(4) i.e.
whichever is the later [15].
There is also scope for a final reference date to be specifically provided.
Conclusion
This insight is not a comprehensive summary of issues that can arise with reference dates. There are plenty more.
Clearly construction contracts entered into before 21 October 2019 are exposed to a larger array of technicalities and show-stoppers than those entered n to after that date, but this is not exclusively the case. The time frames and expense involved in the prosecution of an adjudicated payment claim are material issues for contractors cash-flows. These issues are magnified if the determination is contested.
The simple message is either be across the technicalities or if it is not within your stock in trade, retain a construction specialist lawyer or an experienced security of payment claims consultant to assist you safely navigate through the payment claim graveyard.
Go here to see the original:
Zombie Reference Dates and Payment Claim Graveyards - Lexology
- The Cranberries' Zombie - the story behind the incendiary song - Louder - April 22nd, 2024
- Chris Riddell on the zombie Tory government falling apart at the seams cartoon - The Guardian - April 22nd, 2024
- Zombie grave dating back 4,200 years discovered in Germany, photos show - Miami Herald - April 22nd, 2024
- Steam zombie survival game leaves early access 11 years on, and you've got one week to get it cheap - PCGamesN - April 22nd, 2024
- "Zombie" cicadas with STDs are coming to Virginia - Axios - April 22nd, 2024
- Deathtroopers is the Star Wars zombie horror game I never knew I needed - PC Gamer - April 22nd, 2024
- Zombie Army VR Reveals The Story In Latest Trailer - Bleeding Cool News - April 22nd, 2024
- Where Infected "Zombie Cicadas" In The US Will Emerge In 2024 - TheTravel - April 22nd, 2024
- Zombie anti-abortion laws are menacing American women - The Hill - April 22nd, 2024
- Joe Manganiello to Zombie It Up in Mountain Man Adaptation - Reactor - Reactor - April 22nd, 2024
- Frozen Soul Covered White Zombie and It Rules - MetalSucks - April 22nd, 2024
- Arizona's abortion ban could bring zombie laws back to life in other states - Fast Company - April 22nd, 2024
- Arizona abortion ban shows the dangers of reviving zombie laws - MSNBC - April 22nd, 2024
- Zombie fires smoldering near Canadian oil and gas wells threaten production following 2023 wildfires - WorldOil - April 22nd, 2024
- You'll Never Guess Who Doesn't Want to Repeal a Zombie Abortion Ban - The New Republic - April 22nd, 2024
- Zombie Army VR: New trailer gives a glimpse of the gruesome campaign - MIXED Reality News - April 22nd, 2024
- Zombie Tests: Is the SAT Back From the Dead? - Fair Observer - April 22nd, 2024
- How likely are you to survive a zombie apocalypse in Connecticut? You may want to travel north - Hartford Courant - April 22nd, 2024
- Missouri Reports 162 New Cases Of Deer 'Zombie' Disease In 2023 - Lake Expo - April 22nd, 2024
- Zombie Fires Pose Looming Threat to Canada's Oil and Gas Infrastructure - OilPrice.com - April 22nd, 2024
- Rob Zombie Presenting House on Haunted Hill Soundtrack on Vinyl - ComicBook.com - April 22nd, 2024
- Take on Zombie Stormtroopers In This Star Wars Fan Game - IGN - April 22nd, 2024
- The Best Zombie Game of 2023 Has a New Expansion Out Now - Esports.net News - April 22nd, 2024
- Frozen Soul Debuts Frosty Rendition of White Zombie's 'Creature of the - Knotfest - April 22nd, 2024
- 'Dawn of the Dead' at 45: A Zombie Love Affair That Never Died - The New York Times - April 12th, 2024
- Hyper-sexual 'zombie cicadas' infected with bizarre STD fungus will emerge in US - New York Post - April 12th, 2024
- Zombie malls and other retail centers getting extreme makeovers to keep up with the times - Chicago Tribune - April 12th, 2024
- 'Zombie' drug xylazine found in cannabis THC vapes in UK - BBC.com - April 12th, 2024
- Taxing health insurance: The Republican zombie that refuses to die - Roll Call - April 12th, 2024
- Fungus-infected Zombie Cicadas with hypersexuality to emerge in the US this year: Expert - Hindustan Times - April 12th, 2024
- Zombie Classic Dawn Of The Dead Coming Back to Theaters for 45th Anniversary - MetalSucks - April 12th, 2024
- E-News | 'Zombie cicadas' infected with sexually transmitted fungus expected to emerge this year in parts of US - WVU ENews - April 12th, 2024
- Deadly Zombie Sedative Penetrating The U.K.s Illicit Drugs Market - Forbes - April 12th, 2024
- Seattle Police warn that base ingredient in 'zombie drug' tranq is being sold as standalone pill - FOX 13 Seattle - April 12th, 2024
- Opinion | Today's Opinions: Haunted by zombie law and thrown into abortion time-travel - The Washington Post - The Washington Post - April 12th, 2024
- Rob Zombie Teases 'House of 1000 Corpses' Book With Rare Photos, Original Script and More! - Bloody Disgusting - April 12th, 2024
- Zombie malls getting extreme makeovers to keep up with the times - Detroit News - April 12th, 2024
- 2000s Horror Fantasy Is One Of The Most Unique Takes On The Zombie Genre - Giant Freakin Robot - April 12th, 2024
- Mysterious 'Zombie Neurons' Unlock Secrets of Learning in The Brain - ScienceAlert - April 12th, 2024
- Zombie SKUs: What They Are, How They Work & Results - JumpFly PPC Advertising News - April 12th, 2024
- Arizona Reviving Its Zombie Abortion Ban Is Trump's Doing - The Cut - April 12th, 2024
- Hyper-sexual "zombie cicadas" that are infected with sexually transmitted fungus expected to emerge this year - CBS News - April 12th, 2024
- Should we be concerned about zombie cicadas? - WGN Radio - Chicago - April 12th, 2024
- You need to play this underrated zombie shooter before it leaves Xbox Game Pass - Digital Trends - April 12th, 2024
- End the 'zombie' Comstock Act - Star Tribune - April 12th, 2024
- OPINION - Flesh-eating zombie narcotics are on our streets Britain is badly losing its war on drugs - Yahoo News UK - April 12th, 2024
- What Is Xylazine - The Flesh-Eating 'Zombie' Drug Linked To 11 Deaths in The UK? - Times Now - April 12th, 2024
- Zombie Cicadas To Emerge In Virginia: What To Know - Patch - April 12th, 2024
- What Is "Zombie Drug" Gripping The UK? - NDTV - April 12th, 2024
- OJ Simpson's Final Film Will Resurrect His Naked Gun Character - As A Zombie? - Looper - April 12th, 2024
- Flesh-eating 'zombie drug' sweeping US is linked to 11 UK deaths - The Telegraph - April 12th, 2024
- Flesh-rotting 'Zombie drug' tranq raises alarm in UK - The Times of India - April 12th, 2024
- Zombie Cicadas To Emerge In GA: What To Know - Patch - April 12th, 2024
- What was the first-ever zombie movie? - Far Out Magazine - April 12th, 2024
- Even Will Smith Couldnt Save Zombie Survival Game Undawn, Which Flopped Spectacularly - IGN - March 24th, 2024
- Rob Zombie Recommends This Surprisingly Wholesome Comedy - Dread Central - March 24th, 2024
- Army Writing and the Zombie (Noun) Apocalypse - Modern War Institute - United States Military Academy West Point - March 24th, 2024
- Fatal Fury's Mai Shiranui Is In This Zombie Survival Game For Some Reason - Time Extension - March 24th, 2024
- Should you be worried about 'zombie deer'? | College of Public Health - George Mason University - March 24th, 2024
- 'Scooby-Doo on Zombie Island' Scares Its Way to Blu-ray for the First Time This Spring - Collider - March 24th, 2024
- Rob Zombie hates my guts: GWAR's Dave 'Oderus Urungus' Brockie was a genius, and here's an interview that proves it - Louder - March 24th, 2024
- In the fight against gun violence, Rep. Frost Introduces the Destroy Zombie Guns Act - The Apopka Voice - March 24th, 2024
- Elfriede Jelinek's 'The Children of the Dead' is a historical zombie novel - The Washington Post - The Washington Post - March 24th, 2024
- Germany's Zombie Government Is Fueling the Far Right - The Atlantic - March 24th, 2024
- Zombie Survival Game Undawn Has Crashed And Burned According To A Reuters Report - MMOs.com - March 24th, 2024
- Will Smiths Zombie Game Has Been Hit Harder Than Chris Rock at the Oscars Its Astronomical Budget Was ... - imdb - March 24th, 2024
- Scooby-Doo On Zombie Island / Return to Zombie Island Blu-ray (Warner Archive Collection) - Blu-ray.com - March 24th, 2024
- Registration almost here for Dothans annual Zombie 5K Chase - WDHN - March 24th, 2024
- Zombie magic and gambling club Magic Island will come alive again this summer - Houston Chronicle - March 24th, 2024
- Undawn | The $140m zombie survival game starring Will Smith that bombed while nobody was looking - Filmstories - March 24th, 2024
- After 4 years, a cult classic zombie horror manga from Ga-Rei's creator is finally getting an official English release - Gamesradar - March 24th, 2024
- Will Smith's Zombie Game Has Been Hit Harder Than Chris Rock at the Oscars - Its Astronomical Budget Was ... - FandomWire - March 24th, 2024
- "The game literally no one knew existed": The Will Smith Zombie Survival Game is Reportedly a Big Flop and Fans Are ... - FandomWire - March 24th, 2024
- Zombie-palooza --- Get to the biggest undead music event in the latest Dead Island 2 expansion: SoLA - Gaming Trend - March 24th, 2024
- Bournemouth University medical students treat 'zombie attack' in mass training simulation - The Tab - March 24th, 2024
- Zombie car factories on the rise in China as buyers opt for EVs - Financial Times - March 16th, 2024
- Hey, Remember When Rob Zombie Was Going To Direct THE CROW 3? - FANGORIA - March 16th, 2024
- New Walking Dead Twist Shows How The Zombie Outbreak Will Finally End - Screen Rant - March 16th, 2024
- Candid conversations from death row with The Zombie Hunter - Arizona's Family - March 16th, 2024
- Zombie! The Musical - REVIEW - City Hub Sydney - March 16th, 2024
Reviewed and Recommended by Erik Baquero